1.      The key components of the building construction hoist lift shall be inspected before disassembly. When problems are found, disassembly shall be carried out only after the problems are solved.

2.      1. The key components of the construction hoist shall be inspected before disassembly. When problems are found, disassembly shall be carried out only after the problems are solved.

3.      There should be enough working space as the disassemble site. Warning lines and eye-catching safety warning signs should be set around the area. When disassembling the hoist lift, other operations unrelated to disassembling shall not be carried out in the disassembling operation area.

4.       Disassembly shall not be carried out at night.

5.      When removing the attached wall frame, the height of the free end of the guide rail of the construction lift should always meet the requirements of the operation manual.

6.      It shall be ensured that the guideway frame connected to the foundation can still maintain stability in all directions after the removal of the last attached wall frame.

7.      Disassembly of construction lift shall be carried out continuously. When the disassembly operation cannot be completed continuously, corresponding safety measures should be taken according to the disassembly state.

8.      Before the lifting cage is removed, the non-dismantling personnel shall not carry out activities in the areas such as the lift running passage and elimination inside the ground protective ring fence, the guide rail frame and the attached wall frame.


 